ORIVESI
Orivesi Gold Mine
Sarvisuo Ore Lodes
Mining from the Sarvisuo ore lodes commenced in April 2008 with ore being processed at the Vammala Production Centre 80km to the southwest.
Mining has been conducted from the 260m level to the 620m level with the decline being extended to 620m level. Since recommencing mining at Orivesi 754,443 tonnes of ore have been mined and transported to the Vammala plant.

Orivesi Gold Mine
Kutema Ore Lodes
Kutema was mined by Outokumpu between 1992 and 2003 and produced 422,000 ounces of gold. The 155,900 ounce Indicated and Inferred Resource represents a substantial medium to high grade depth extension.
Following the completion of an internal study the Company committed to a staged development of the Kutema lodes. The study highlighted the potential to the 1080m level.
The extension of the Kutema decline from the 720m level commenced in January 2011, had advanced 686m by the end of December 2011 and reached the 820m level.
Lateral development also advanced 790m in 2011 at the 740m, 760m, 780m, 800m and 820m levels. Mining of stopes from Kutema is expected to commence in July 2012.